Thrissur
Report

 

Pradhan Mantri Awas Yojana-LIFE

Thrissur Municipal Corporation

 

Housing Demand

  • HFAPoA got approval
  • Beneficiary Led New House Construction: 994 sanctioned, data cleaning process initiated
  • Affordable Housing in Partnership: 1737
  • Credit Linked Subsidy: 826

 

DPR Approved in BLC New

DPR Phase

No of Beneficiaries

Project Cost (In Lakhs) As per DPR

Project Cost As per New fund sharing pattern (In Lakhs)

Phase 1 DPR

270

810

1320

Phase 2 DPR

204

612

816

Phase 3DPR

491

1473

1964

Phase 4 DPR

29

116

116

Total

994

3011

4216

 

BLC New Implementation Status

DPR Phase

No of Beneficiaries

1st instalment released

2nd instalment released

3rd instalment released

4th instalment released

Expenditure (In lakhs)

Phase 1 DPR

270

147

131

112

63

376.42

Phase 2 DPR

204

99

     82

 66

  27

        258.62

Phase 3 DPR

491

184

 136

71

 4

        370.55

Phase 4 DPR

29

7

   5

 1

  0

        12.2

Total

994

437

354

250

94

        1017.79

 

Fund Status( In Lakhs)

DPR Phase

Central & State Share Needed

Central & State Share Allotted

ULB Share Needed

ULB Share Allotted

Phase 1 DPR

540

200

420

420

Phase 2 DPR

408

0

408

408

Phase 3DPR

982

0

982

240.05

Phase 4 DPR

58

0

58

0

Total

1988

200

1868

1068.05

 

 

MIS & Geo Tagging Status

 

DPR Phase

No of Beneficiaries

MIS Attachment

MIS Attachment %

Aadhar Validation

Aadhar Validation %

Geo Tagging Houses

Geo Tagging % of sanctioned

Phase 1 DPR

270

247

91.48%

247

91.48%

136

50.37%

Phase 2 DPR

204

203

99.51%

       203

99.51%

      102

   50%

Phase 3DPR

491

469

95.52%

469

95.52%

175

35.64%

Phase 4 DPR

29

29

100%

29

100%

10

34.48%

Total

994

948

95.37%

948

95.37%

423

42.55%

 

AHP-Affordable Housing In Partnership

  • Total Landless homeless: 1737
  • Land Identified : 1 acre identified
  • Council Decision & Feasibility Report submitted

 

CLSS- Credit Linked Subsidy Scheme

  • Total Demand: 826
  • NOC Given: 210
  • Loan Sanctioned: 242
  • Subsidy Released: 106

 

Activities Planned

  1. Data Cleaning

-Process initiated

-Ward wise list given to Councillors

-Ward wise list given to Kudumbashree CDS

-Note given in News papers

-Planned to send letter to beneficiaries

 

  1. Area wise Beneficiary meetings for CpmpletingData Cleaning and convergence with NULM &AyyankaliThozhilurappu scheme

 

- Gap Analysis (Construction Status, Bottlenecks, NHG membership status, Need for self employment, need for skill training, Ayyanaklithozhil card, welface schemes access etc will be analysed)

-Schedule for Beneficiary meeting:

Date

Venue

Wards

18.07.2018

Diet Hall

4, 5, 6, 7, 8, 9

19.07.2018

Tagore Hall

36, 37, 38, 39, 45, 46, 47, 48, 49

20.07.2018

Tagore Hall

50, 51, 52, 53, 54, 55, 1, 2, 3

21.07.2018

Ollur Community Hall

24, 25, 26, 27, 28, 29, 30, 31

23.07.2018

Koorkkanchery Community Hall

32, 33, 34, 35, 40, 41, 42, 43, 44

24.07.2018

Ollukkara Community Hall

10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23 175

 

 

 

  1. Engage MSW Students in campaign for speedy implementation & Social Development Activities

-Discussed with Vimala College

-Department of Social Work is willing to allot MSW students for field work in PMAY

-Gap Analysis & convergence with all welfare schemes

 

  1. Free Gas Connection to all eligible PMAY beneficiaries in convergence with PM Ujjwala Yojana

 

Way ahead

  • Data Cleaning and submission of revised list on or before August 20
  • Building permit for all eligible by September 30
  • Agreement Execution of all eligible by October 20
  • 100% Geo Tagging by August 30
  • 100% NHG Inclusion by September 30
  • AyyankaliThozhil Card for PMAY Beneficiaries
  • Free Gas Connection to all eligible PMAY beneficiaries