PMAY Progress
Report

Total houses identified in survey       : 1364

Insitu slum development                   : 0

Credit Linked Subsidy                      : 534

Affordable Housing in Partnership   : 280

Beneficiary led House construction : 550

Total Approved DPR                        : 3

Beneficiaries in I DPR                     : 270

Beneficiaries in II DPR                    : 260

Beneficiaries in III DPR                   : 12

Total houses started construction   : 271

Total houses completed                 : 8

No of Houses geo tagged              : 321

No of points geo tagged                : 475

Total project Cost                          : 1626 lakhs

Government of India share           : 813 lakhs 

Government of India share received : 131.25 lakhs

Governemt of Kerala share          : 271 lakhs

Government of Kerala share received 43.75 lakhs

Municipal share                            : 273 lakhs

Municipal share received             : 108.65 lakhs

Beneficiary share                         : 269 lakhs

Beneficiary share received           : 39.20 lakhs

Total fund disbursed                     : 312 lakhs

Credit Linked subsidy sanctioned  : 120

CLSS subsidy received                 : 19

AHP land identified                       : 2.2 acre

Activities in Municipality

1. Non started beneficiary meeting conducted in Municipality. The meetings conducted in 3 days and 1/3 wards participated in a day. It was conducted in February 2018. Several number of beneficiaires are not participated in the meeting conducted in Municipality. So ward wise meetings arranged. It was helped to identify ineligible beneficiaries. It was conducted in April-May 2018

2. Data cleaning completed and 59 beneficiaries are ineligible. The consent from beneficiaries are receiving 

3. Geo tagging of non agreement executed beneficiaries are started and will be  complete by July 30

4. Enrolled 46 PMAY Beneficiaries in AUEGS. The enrollment process will be completed by July 2018

Activities Planned for speed up implementation 

1. Incompleted beneficiary meeting planned on 19.7.2018

2. The II phase Ward level meetings of of non agreement executed beneficiaries in July - August 2018

3. The Municipality is trying to ensure free gas coneection for all PMAY beneficiaries through Pradhan Mantri Ujjal Yojana. The process of enrolling all eligible beneficiaries to Pradhan Mantri Ujjal Yojana is progressing.